How to remodel a bathroom in the right order
The materials for a 5-by-8 hall bath cost $1,545.67 at September 2026 retail prices, about 6% of the $26,138 a contractor-built midrange bath ran in JLC's 2025 Cost vs Value report.
Remodel a bathroom in this order: plan and permit, demolition, subfloor and framing repair, rough plumbing and electrical, rough inspection, tub and backer board, waterproofing, tile and grout, drywall and paint, fixtures, final inspection. Each step covers the one before it, so each gets checked before it disappears.
| Time, one person | About 19 working days, plus inspection waits |
| DIY materials, 5-by-8 hall bath | $1,545.67, plus a $309 reserve (20%) |
| Contractor price, similar job | $26,138 for a midrange 5-by-7 (JLC Cost vs Value 2025) |
| Difficulty | Hard. It stacks five trades in a small room. |
| Permit | Yes for new plumbing, a new circuit or a new fan duct (2021 IRC R105.1). Tile and cabinets alone are exempt (R105.2). |
| Do not DIY | Plumbing and wiring your jurisdiction reserves for licensed trades, and paid work on painted surfaces in a pre-1978 house (EPA RRP) |
Prices seen September 19, 2026 at Menards and Ace Hardware. Check your city's permit rules before demolition.
The case: a 5-by-8 hall bath with a tub
Every number below belongs to one room. The bath is 5 by 8 feet with an 8-foot ceiling. A 60-by-30-inch alcove tub with a shower head fills the 5-foot end wall, and the toilet and a 30-inch vanity share the long wall. The door is 30 by 80 inches. The layout stays put, and that decision is what keeps the job at this price.
The floor is 12-by-24 porcelain, 27.5 sq ft once the tub footprint is subtracted. The surround is 3-by-6 ceramic on three walls, from the tub rim (about 14-1/4 inches up) to 84 inches above the floor, 58.1 sq ft in all; the code minimum is 6 feet above the floor (IRC R307.2). The other walls and the ceiling get 1/2-inch mold and moisture resistant drywall.
Check clearances before buying anything. IRC P2705.1 wants the toilet centered at least 15 inches from any side wall or vanity, with 21 inches clear in front. In a 5-foot-wide room those numbers decide whether toilet and vanity can share a wall.
What order do you remodel a bathroom in?
Work from the structure out to the finishes, twelve steps in all. Each step ends with the check that tells you it is done right. Nothing gets covered until it has been tested and inspected (2021 IRC P2503.2). Code sections on this page are from the 2021 IRC; your city may have adopted another edition or local amendments.
-
1. Plan, order and apply for permits
Draw the room to scale, pick every product, confirm the tub's drain side matches the existing drain, and file the permit. Order all tile from one production lot.
Check: every fixture meets the 15-inch and 21-inch clearances of P2705.1 on paper, and the permit is issued before demolition starts.
-
2. Demolish down to studs and subfloor
Shut off water and the bathroom circuit at the panel, cap the supplies, plug the toilet flange with a rag, then remove fixtures, tile, backer and drywall. The section on removing a bathroom below has the details.
Check: bare studs, a clean subfloor and a clear view of every pipe and joist in the room.
-
3. Repair subfloor and framing, add blocking
Probe the subfloor around the toilet flange and the tub drain with an awl. Replace any soft section back to sound framing. Add blocking for the vanity, grab bars and the valve. USG limits stud spacing behind Durock to 16 inches on center, and TEC's thinset sheet sets the floor deflection limit for ceramic tile at L/360.
Check: a 4-foot level shows the floor flat enough for 12-by-24 tile, and no board moves when you stand on it.
-
4. Rough plumbing and electrical
Install the tub/shower valve, which must be pressure-balanced or thermostatic with a limit stop set so water does not exceed 120°F (P2708.4). Connect the tub drain and overflow. Run the bathroom receptacle on its own 20-amp circuit (E3703.4), place a receptacle within 36 inches of the basin (E3901.6), protect it with a GFCI (E3902.1), and duct the fan directly outdoors (R303.3), sized for at least 50 cfm intermittent (Table M1505.4.4). This is the permitted step. Where your jurisdiction reserves plumbing or wiring for licensed trades, a licensed plumber and electrician do it and pull the permits; where owners may do it, the same inspections apply. The guide to replacing a tub or shower faucet covers the valve swap on its own.
Check: the drain system holds water 10 feet above the highest fitting, or 5 psi of air, for 15 minutes (P2503.5.1), and the supply piping holds working pressure for 15 minutes (P2503.7).
-
5. Rough inspection
Book it once step 4 passes your own test.
Check: a signed rough inspection card. Do not close a wall without it.
-
6. Set the tub
Set it level on the support the manufacturer specifies, fasten the flange to the studs, connect the drain and cover the finish.
Check: a level on the rim reads flat both ways, and a full tub drains without a drip at the overflow or shoe.
-
7. Hang cement board and drywall
In the surround, hang 1/2-inch cement board with fasteners every 8 inches, tape the joints with alkali-resistant mesh set in thinset, and hold the bottom edge off the tub lip with a 1/4-inch spacer strip (USG). Outside the surround, hang drywall. On the floor, set 1/4-inch cement board in thinset and screw it down.
Check: no drywall behind tile in the wet zone (R702.4.2), and the 1/4-inch gap at the tub is still open.
-
8. Waterproof the surround
Roll TEC HydraFlex in two coats of 25 mils wet each, the second at right angles to the first, about an hour apart. The data sheet puts coverage at 50 sq ft per gallon for this two-coat waterproofing application.
Check: an unbroken dark purple film with no light spots or pinholes, 2 to 12 hours after the second coat.
-
9. Tile the walls, then the floor
Start the wall tile from a level line one course above the tub, never from the tub rim, and keep a 1/8-inch gap at the tub. Set the floor last so you are not kneeling on it. Use a 1/4-by-3/8-inch notch on the 12-by-24 floor tile and back-butter it.
Check: pull a tile after the first few minutes. The back should be fully covered with mortar, and the courses should stay level across all three walls.
-
10. Grout and caulk
TEC says to grout Full Flex installations once the tiles are held firmly in place, typically 16 to 24 hours after setting. Fill the change-of-plane joints (inside corners, the tub line, the floor edge) with silicone rather than grout.
Check: full, flat grout joints with no pinholes, and flexible sealant at every corner.
-
11. Finish drywall, prime and paint
Tape, coat, sand, prime and paint.
Check: no joint visible in raking light.
-
12. Set the fixtures and pass the final
Install the valve trim, set the toilet on a new seal (the toilet installation guide covers it), set the vanity and faucet (the sink faucet guide ends with the install), and finish the fan and receptacle. Fill and drain every fixture: IRC P2503.5.2 asks for traps and connections that are watertight by visual inspection.
Check: a signed final inspection and a dry paper towel under every connection after 24 hours of use.
How do you remove a bathroom down to the studs?
Start by shutting off water and power. Close the fixture stops and the main, open a faucet downstairs to drain the lines, and turn off the breaker for the bathroom circuit, then verify it with a tester. Remove the toilet first and stuff the flange with a rag so sewer gas and debris stay out.
Pull the vanity, then the surround. Tile on cement board comes off in sections if you cut the board along the studs; tile on a mortar bed needs a rotary hammer. A steel tub comes out easier cut in half with a reciprocating saw. Strip the drywall to the studs so every pipe, wire and joist is visible.
Two things stop the job. In a pre-1978 house, anyone you pay to disturb painted surfaces must be an EPA-certified firm under the RRP rule; owners working on their own home are generally outside it. Being outside the rule does not make the dust safe. Test the paint on trim and walls before demolition, and if it contains lead, either hire a certified firm or work lead-safe: plastic sheeting, no dry sanding or torch stripping, and a HEPA vacuum for cleanup. And any old flooring or wall material that might contain asbestos gets tested before anyone breaks it.
Do you need a permit to remodel a bathroom?
Yes for new plumbing, a new circuit or a new fan duct; no for tile, cabinets and paint alone. The model code puts it simply. IRC R105.1 requires a permit to "install, enlarge, alter, repair, remove, convert or replace" any plumbing, electrical, gas or mechanical system. R105.2 then lists what is exempt. Finish work is exempt: painting, tiling, cabinets, countertops. Clearing stoppages and repairing leaks are exempt. Removing and reinstalling a toilet is exempt, as long as no valve, pipe or fixture is replaced or moved.
| Work in this remodel | Permit under the 2021 IRC | Who usually does it |
|---|---|---|
| Demolition, tile, vanity, paint | Exempt as finish work (R105.2) | Owner |
| New tub/shower valve and tub drain | Required (R105.1) | Licensed plumber, or owner where local law allows |
| Replacing the toilet with a new one | Outside the R105.2 exemption, since a fixture is replaced; many cities treat it as minor | Owner or plumber |
| Moving a drain or the toilet | Required; new drain work | Licensed plumber |
| New 20-amp circuit, GFCI, fan with outside duct | Required | Licensed electrician, or owner where allowed |
| Structural repair to joists | Required | Carpenter; engineer if joists were cut |
Whether an owner may pull plumbing and electrical permits for the house they live in is a local decision. Ask when you apply. The inspection happens either way.
How long does a bathroom remodel take?
About 19 working days for one person on this 5-by-8 bath, plus inspection waits. The table is my plan for one competent person working full days, with cure times taken from the product sheets. Inspection waits are left out because they depend entirely on your building department.
| Phase | Working days | What sets the pace |
|---|---|---|
| Plan, order, permit application | before day 1 | Tile and tub lead times, permit review |
| Demolition and haul-out | 2 | Disposal logistics |
| Subfloor repair and blocking | 1 | More if rot is found |
| Rough plumbing and electrical, tests | 2 | 15-minute tests per P2503 |
| Rough inspection | wait | Local scheduling |
| Set tub | 1 | Tub support and drain connection |
| Cement board, floor underlayment, drywall hang | 2 | Fastening every 8 inches |
| Waterproofing, two coats and flood check | 1 | 2 to 12 hours after second coat |
| Wall and floor tile | 3 | 490 wall tiles and 15 floor tiles |
| Grout and silicone | 1 | 16 to 24 hours after setting |
| Drywall taping and coats | 3 | One coat a day |
| Prime and paint | 1 | Dry time between coats |
| Fixtures, trim, fan, receptacle | 2 | Leak checks |
| Total, before inspection waits | 19 |
Nineteen working days is roughly four weeks of weekdays, or about ten weekends. In a one-bathroom house, plan for the toilet's absence first.
How much does it cost to remodel a bathroom yourself?
Materials for this 5-by-8 hall bath came to $1,545.67 at September 19, 2026 prices, before permit, disposal, paint and fittings. Quantities for tile come from the tile calculator's math. The floor needs 15 tiles of 12-by-24 porcelain at 10% waste; the surround needs 490 tiles of 3-by-6 ceramic in a running bond at 12% waste, with 1/8-inch joints. Grout for both works out to 9.7 lb, so one 25-lb bag covers it. The drywall calculator's math gives 7 sheets of 4-by-8: 5 for the walls and 2 for the ceiling at 10% waste. Cement board for the surround is 5 sheets of 3-by-5 from the layout (two on the back wall, three for the ends), plus 2 sheets of 1/4-inch board for the floor. The membrane needs 58.1 sq ft ÷ 50 sq ft per gallon = 1.16 gallons, so two 1-gallon pails.
Your floor and your surround, tile by tile, with the waste and the grout:
| Line (prices seen 2026-09-19) | Quantity and unit price | Cost |
|---|---|---|
| Alcove tub, 60 x 30, steel, right drain (Briggs Pendant V) | 1 at $219.00 | $219.00 |
| Tub drain and overflow, toe touch | 1 at $31.99 | $31.99 |
| Pressure-balance valve body (Moen Posi-Temp) | 1 at $89.99 | $89.99 |
| Valve trim kit | 1 at $54.99 | $54.99 |
| Toilet (American Standard Titan, elongated, sale price) | 1 at $208.98 | $208.98 |
| Toilet seat, wax ring, flange bolts, supply line | $16.99 + $2.79 + $4.98 + $8.99 | $33.75 |
| Vanity with cultured marble top, 30-1/2 in. | 1 at $149.99 | $149.99 |
| Faucet (Moen Adler 4 in. centerset) and 2 supply lines | $59.00 + 2 at $9.99 | $78.98 |
| Exhaust fan, 80 cfm | 1 at $69.00 | $69.00 |
| 20-amp GFCI receptacle | 1 at $17.17 | $17.17 |
| Cement board 1/2 x 3 x 5 | 5 at $16.35 | $81.75 |
| Cement board 1/4 x 3 x 5 (floor) | 2 at $13.13 | $26.26 |
| Cement board screws (5 lb) and mesh tape | $16.99 + $8.99 | $25.98 |
| Waterproofing membrane (TEC HydraFlex, 1 gal) | 2 at $52.99 | $105.98 |
| Thinset (TEC Full Flex, 50 lb) | 2 at $24.99 | $49.98 |
| Floor tile, 12 x 24 porcelain | 15 at $3.88 | $58.20 |
| Wall tile, 3 x 6 ceramic | 490 at $0.13 | $63.70 |
| Sanded grout, 25 lb | 1 at $13.99 | $13.99 |
| Mold and moisture resistant drywall 1/2 x 4 x 8 | 7 at $22.00 | $154.00 |
| Silicone sealant, kitchen and bath | 1 at $11.99 | $11.99 |
| Materials total | $1,545.67 | |
| Reserve, 20% (my allowance) | $309.13 | |
| Permit, disposal, paint, light fixture, pipe and wire fittings | set locally | not included |
Grouped the way the work is sequenced, the split looks like this:
| Group | Cost | Share |
|---|---|---|
| Tub, drain, valve and trim | $395.97 | 25.6% |
| Toilet and its parts | $242.73 | 15.7% |
| Backer board, membrane, fasteners | $239.97 | 15.5% |
| Vanity, faucet, supplies | $228.97 | 14.8% |
| Tile, thinset, grout | $185.87 | 12.0% |
| Drywall and sealant | $165.99 | 10.7% |
| Fan and GFCI | $86.17 | 5.6% |
| Total | $1,545.67 | 100% |
The tile itself is $121.90 of the total, and the membrane under it costs almost as much ($105.98). The membrane decides whether the tile lasts. JLC's midrange spec runs $26,138 for a slightly smaller 5-by-7 room; subtract $1,545.67 and $24,592.33 is left for labor, subcontractors, overhead, profit, permits, disposal and some nicer finishes (a solid-surface counter, a recessed medicine cabinet). Materials are about 6% of a contractor-built bath at this level, which is why doing the work yourself moves the budget far more than cheaper tile does.
Tools: what you need, what to rent
You need a 4-foot level, a drill/driver, a reciprocating saw, notched trowels (1/4 by 1/4 inch for walls, 1/4 by 3/8 inch for the floor), a grout float, a mixing paddle, a manual tile cutter, drywall knives and a voltage tester. Rent a wet saw for the porcelain, and a rotary hammer if the old tile sits on a mortar bed. A laser level is a luxury. Wear a respirator rated for silica when cutting cement board or porcelain.
Where bathroom budgets blow up
Two surprises cause most overruns when the layout stays put, and one decision causes most of the rest.
Subfloor rot comes first. Small leaks at the wax ring and the tub drain soften the subfloor where you cannot see it, and you find it after demolition. The material is cheap: a sheet of 3/4-inch tongue-and-groove OSB was $26.98. The cost is in the time. A soft area that reaches a joist means cutting back to sound wood, sistering the joist, and adding blocking. At the national median carpenter wage loaded with benefits, $41.90 an hour, each 8-hour day of a carpenter's time is at least $335 before any contractor markup.
Moving a drain is the decision that changes the job. Keep the toilet and tub in place and the plumbing is a swap. Move them and the new drain has to meet slope and structure rules at once. IRC P3005.3 requires a slope of 1/4 inch per foot on drains of 2-1/2 inches and smaller, and 1/8 inch per foot on 3-inch and larger. IRC R502.8.1 limits bored holes in a joist to one third of its depth, kept 2 inches from the top and bottom edges. A 2x8 joist is 7-1/4 inches deep, so the largest hole allowed is about 2.4 inches, and a 3-inch drain pipe does not fit through it. Running a toilet drain across joists then means headers, a dropped ceiling below or a different route, plus a plumber and a permit. That is why this budget keeps the layout.
The mistakes that cost money are specific, and each has a repair bill:
| Mistake | What it causes | Materials to redo, at the prices above |
|---|---|---|
| Skipping the membrane in the surround | Water through grout into the backer and studs | $290.41 (tile, backer, membrane, thinset, grout) plus fasteners and the demolition |
| Drywall instead of a listed backer in the wet zone (R702.4.2) | Failed inspection or a wall that softens | $81.75 of cement board plus the tile over it |
| Backer board sitting on the tub lip | Water wicks up into the board | Rework of the bottom course; the 1/4-inch spacer costs nothing |
| Fan vented into the attic | Fails R303.3; moisture in the attic | A duct run and roof or wall cap, plus a reinspection |
| Tile bought short, second trip lands a different lot | Visible shade change | $63.70 to rebuy the full wall run |
| Covering pipes before the rough inspection | Inspector can require opening walls (P2503.2) | Drywall or backer rebuy plus lost days |
The first row is the whole redo list: wall tile $63.70, cement board $81.75, membrane $105.98, one bag of thinset $24.99 and grout $13.99. Skipping the membrane saves $105.98 and puts the surround at risk.
How much contingency should you hold?
Hold back 20% of the materials budget on a do-it-yourself job, $309.13 here, and do not spend it on upgrades before demolition is finished. On a contractor bid, ask how the contract handles concealed conditions such as rot, and keep 10% of the bid available in cash or credit. Both are my allowances, sized from the two surprises above.
If the reserve has to be borrowed, the renovation financing guide compares HELOC, home equity loan, cash-out refinance and cash at September 2026 rates.
Do it yourself or hire: the trade math
Split the job by trade and price each hour you take on. The table uses the May 2025 BLS medians, loaded to a full employer cost with the June 2026 BLS ECEC ratio for the private construction industry (wages are 69.5% of compensation, $36.13 of $51.96 an hour). A contractor's hourly bill is higher than this, since it also covers the truck, insurance, overhead and profit. So these are floors: each hour you work displaces at least this much.
| Trade (BLS OEWS, May 2025) | Median wage | Loaded hour | 10 hours of your own work displaces at least |
|---|---|---|---|
| Plumbers (47-2152) | $30.67 | $44.13 | $441 |
| Electricians (47-2111) | $30.38 | $43.71 | $437 |
| Carpenters (47-2031) | $29.12 | $41.90 | $419 |
| Drywall installers (47-2081) | $28.33 | $40.76 | $408 |
| Tile and stone setters (47-2044) | $26.77 | $38.52 | $385 |
Plumber wages vary a lot by state, which moves the case for hiring the rough-in. The median was $25.44 in Florida, $35.01 in California, $37.26 in New York and $48.05 in Illinois, which load to $36.60, $50.37, $53.61 and $69.14 an hour.
A split that works for most owners: hire licensed trades for the valve, drain connection, circuit and fan duct, the permitted parts that fail expensively. Do demolition, backer, waterproofing, tile, drywall and paint yourself. Those hours fill the 19-day schedule, and they are where most of the $24,592 gap goes. A tile setter covers more square footage per hour than you will, so count savings per job.
Frequently asked questions
What order do you remodel a bathroom in?
Permits, demolition, subfloor and framing repair, rough plumbing and electrical, rough inspection, tub, cement board and drywall, waterproofing, tile and grout, drywall finish and paint, fixtures, final inspection. Nothing gets covered before it is inspected (2021 IRC P2503.2), and each wet layer is finished before the next one goes on.
Do you need a permit to remodel a bathroom?
Usually yes, for the plumbing and electrical parts. The 2021 IRC, section R105.1, requires a permit to install, alter, repair or replace plumbing or electrical systems. R105.2 exempts finish work such as tiling and cabinets, leak repairs, and removing and reinstalling a toilet without replacing or moving pipes, valves or fixtures. A new shower valve, a moved drain, a new circuit or a new vented fan needs one. Your city's adopted code is what counts, so ask before demolition.
How long does it take to remodel a bathroom by yourself?
About 19 working days for one person on the 5-by-8 bath on this page, plus inspection waits. The product waits are fixed: 2 to 12 hours after the second membrane coat before a flood test, and 16 to 24 hours between setting tile and grouting. Tile and drywall finishing take the most calendar time.
How much does it cost to remodel a bathroom yourself?
Materials for a 5-by-8 hall bath with a new tub, toilet, 30-inch vanity and tiled surround and floor came to $1,545.67 on September 19, 2026, before permit, disposal, paint and fittings. Add a $309 reserve and whatever you pay licensed trades. JLC's 2025 Cost vs Value put a contractor-built midrange 5-by-7 bath at $26,138.
Can I tile over drywall in a tub surround?
Not in the wet zone. IRC R702.4.2 limits backers for tile in tub and shower areas to glass mat gypsum, fiber-reinforced gypsum, fiber-cement and cementitious backer units such as 1/2-inch cement board. Moisture-resistant drywall belongs outside the surround. R307.2 requires the nonabsorbent finish to reach at least 6 feet above the floor over a tub with a shower head.
How do I redo a bathroom on a budget?
Keep every drain and the toilet where they are, since moving one turns finish work into new plumbing under the joist limits of IRC R502.8.1. Then do the unlicensed trades yourself: demolition, tile, drywall and paint. Every 10 hours of tile you set displaces at least $385 of a tile setter's wage cost at the 2025 national median.
Sources
- ICC, 2021 International Residential Code, Chapter 1, Sections R105.1 and R105.2 : Permit required to install, alter, repair or replace plumbing or electrical systems; exemptions for painting, papering, tiling, carpeting, cabinets, counter tops and similar finish work, for clearing stoppages and repairing leaks, and for removing and reinstalling water closets without replacing or rearranging valves, pipes or fixtures. Accessed 2026-09-19.
- ICC, 2021 IRC, Chapter 25, Section P2503 (inspection and tests) : P2503.2: no plumbing covered or put into use until tested, inspected and approved; P2503.5.1 DWV rough test: water to 10 ft above highest fitting for 15 minutes, or 5 psi air, or 5 psi vacuum on plastic; P2503.6 shower liner test: 2 in. of water at the threshold for 15 minutes; P2503.7 water supply test at working pressure for 15 minutes. Accessed 2026-09-19.
- ICC, 2021 IRC, Chapter 27 (plumbing fixtures) : P2705.1: toilet, lavatory or bidet at least 15 in. from center to side wall or vanity, 30 in. center to center, 21 in. clear in front; P2708.4: shower and tub/shower valves must be pressure-balanced or thermostatic with a 120°F limit stop; P2709.2: lining materials for built-up shower receptors. Accessed 2026-09-19.
- ICC, 2021 IRC, Chapter 3, Sections R303.3 and R307.2 : R303.3: bathrooms need 3 sq ft of glazing, half openable, unless artificial light and local exhaust are provided, exhausted directly outdoors; R307.2: walls above tubs with shower heads finished with a nonabsorbent surface at least 6 ft above the floor. Accessed 2026-09-19.
- ICC, 2021 IRC, Chapter 7, Section R702.4.2 (backer boards) : Backers for wall tile in tub and shower areas: ASTM C1178, C1278, C1288 or ISO 8336 Category C, C1325; installed per manufacturer. Accessed 2026-09-19.
- ICC, 2021 IRC, Chapter 15, Table M1505.4.4 : Bathrooms and toilet rooms: 50 cfm intermittent or 20 cfm continuous, rated at 0.25 in. water column. Accessed 2026-09-19.
- ICC, 2021 IRC, Chapters 37 and 39 (E3703.4, E3901.6, E3902.1) : At least one 20-ampere circuit for bathroom receptacles (E3703.4, chapter 37); a receptacle within 36 in. of each basin (E3901.6); GFCI protection for bathroom receptacles (E3902.1). Accessed 2026-09-19.
- ICC, 2021 IRC, Chapter 5, Section R502.8.1, and Chapter 30, Section P3005.3 : Joist notches no deeper than 1/6 of depth and not in the middle third of the span; bored holes no larger than 1/3 of depth and at least 2 in. from top and bottom. P3005.3 (chapter 30): drain slope 1/4 in. per ft for 2-1/2 in. and smaller, 1/8 in. per ft for 3 in. and larger. Accessed 2026-09-19.
- U.S. EPA, Lead Renovation, Repair and Painting Program : Anyone paid to disturb painted surfaces in homes built before 1978 must be certified; the rule generally does not apply to owners working on their own home unless it is rented, a childcare facility or a flip. Accessed 2026-09-19.
- USG, Durock Brand Cement Board Installation Guide : Studs 16 in. o.c. maximum; fasteners 8 in. o.c. on walls, 6 in. on ceilings; joints filled with latex-fortified mortar and alkali-resistant mesh tape; 1/4 in. spacer strip on the tub lip to hold the panel off the fixture. Accessed 2026-09-19.
- TEC, HydraFlex Waterproofing Crack Isolation Membrane 316, product data sheet (r0925) : Waterproofing: 2 coats of 25 mils wet, 50 sq ft per gallon; first coat dries about 1 hour; ready for flood testing 2 to 12 hours after the second coat; ready for tile in 1 to 3 hours. Accessed 2026-09-19.
- TEC, Full Flex Latex Modified Thin Set Mortar 390/391, product data sheet : Coverage per 50 lb: 95 to 105 sq ft with a 1/4 x 1/4 in. square notch, 70 to 80 sq ft with 1/4 x 3/8 in.; grout typically 16 to 24 hours after installation; substrate deflection limit L/360 for ceramic tile. Manufacturer sheet hosted by distributor L. Fishman. Accessed 2026-09-19.
- Menards, product and search pages (prices seen 2026-09-19, store prices vary) : Briggs Pendant V 60 x 30 bathtub SKU 6713140 $219.00; Plumb Works toe touch drain 6798414 $31.99; Moen Posi-Temp rough-in valve 6748789 $89.99; Posi-Temp trim kit 6748796 $54.99; American Standard Titan elongated toilet 6703866 $208.98 (sale price); Mayfair Westport seat 6762201 $16.99; Harvey No. 1 wax ring 6642569 $2.79; Danco flange bolts 6641290 $4.98; Fluidmaster 20 in. supply 6640519 $8.99; Designer's Image Winston 30-1/2 in. vanity with top 4831007 $149.99; Moen Adler 4 in. centerset faucet 6735004 $59.00; Broan 80 cfm fan 6112351 $69.00; Legrand 20 A GFCI 3637171 $17.17; Durock 1/2 x 3 x 5 1315000 $16.35; PermaBASE UltraBacker 1/4 x 3 x 5 1315039 $13.13; Grip Fast cement board screws 5 lb 2294348 $16.99; FibaTape 2 in. mesh 1314987 $8.99; TEC HydraFlex 1 gal 7056922 $52.99; TEC Full Flex 391 50 lb 7056808 $24.99; Mohawk Ristoria 12 x 24 porcelain 7386430 $3.88 each; Mohawk Vivant 3 x 6 ceramic 7350420 $0.13 each; TEC AccuColor sanded grout 25 lb 7056774 $13.99; 1/2 x 4 x 8 mold and moisture resistant drywall 1311256 $22.00; 3/4 x 4 x 8 T&G OSB subfloor 1242867 $26.98; GE Supreme kitchen and bath silicone 5639365 $11.99.
- Ace Hardware, 3/8 in. compression x 1/2 in. FIP 20 in. stainless supply line : $9.99 each, seen 2026-09-19.
- JLC Cost vs Value 2025, Bath Remodel Midrange (aggregator, cross-check only) : Update an existing 5x7 bathroom: 30x60 porcelain-on-steel tub, 4x4 ceramic tile surround, pressure-balanced shower control, standard toilet, solid-surface vanity counter, recessed medicine cabinet, ceramic tile floor, vinyl wallpaper. National cost $26,138, resale value $20,915, 80% recouped. Accessed 2026-09-19.
- BLS, Occupational Employment and Wage Statistics, May 2025 : National median hourly wage: plumbers 47-2152 $30.67; electricians 47-2111 $30.38; tile and stone setters 47-2044 $26.77; carpenters 47-2031 $29.12; drywall installers 47-2081 $28.33. Plumber medians by state: CA $35.01, IL $48.05, NY $37.26, FL $25.44. Accessed 2026-09-19.
- BLS, Employer Costs for Employee Compensation, Table 4 (June 2026) : Private construction industry: wages and salaries are 69.5% of total compensation ($36.13 of $51.96 per hour). Accessed 2026-09-19.